The turbines run-down energy capability still needed to be confirmed experimentally, and previous tests had ended unsuccessfully. An initial test carried out in 1982 indicated that the excitation voltage of the turbine-generator was insufficient; it did not maintain the desired magnetic field after the turbine trip. The electrical system was modified, and the test was repeated in 1984 but again proved unsuccessful. In 1985, the test was conducted a third time but also yielded no results due to a problem with the recording equipment. The test procedure was to be run again in 1986 and was scheduled to take place during a controlled power-down of reactor No. 4, which was preparatory to a planned maintenance outage.
A test procedure had been written, but the authors were not aware of the unusual RBMK-1000 reactor behaviour under the planned operating conditions. It was regarded as purely an electrical test of the generator, not a complex unit test, even though it involved critical unit systems. According to the existing regulations, such a test did not require approval by either the chief design authority for the reactor (NIKIET) or the nuclear safety regulator. The test program called for disabling the emergency core cooling system, a passive/active system of core cooling intended to provide water to the core in a loss-of-coolant accident, and approval from the site chief engineer had been obtained according to regulations.
The test procedure was intended to run as follows:
Test preparation
1. The test would take place prior to a scheduled reactor shutdown
2. The reactor thermal power was to be reduced to between 700 MW and 1,000 MW (to allow for adequate cooling, as the turbine would be spun at operating speed while disconnected from the power grid)
3. The steam-turbine generator was to be run at normal operating speed
4. Four out of eight main circulating pumps were to be supplied with off-site power, while the other four would be powered by the turbine
Electrical test
1. When the correct conditions were achieved, the steam supply to the turbine generator would be closed, and the reactor would be shut down
2. The voltage provided by the coasting turbine would be measured, along with the voltage and revolutions per minute (RPMs) of the four main circulating pumps being powered by the turbine
3. When the emergency generators supplied full electrical power, the turbine generator would be allowed to continue freewheeling down
The test was to be conducted during the dayshift of 25 April 1986 as part of a scheduled reactor shut down. The day shift had been instructed in advance on the reactor operating conditions to run the test, and a special team of electrical engineers was present to conduct the one-minute test of the new voltage regulating system, once the correct conditions were reached. As planned, a gradual reduction in the output of the power unit began at 01:06 on 25 April, and the power level had reached 50% of its nominal 3,200 MW thermal level by the beginning of the day shift.
The day shift performed many unrelated maintenance tasks, and was scheduled to perform the test at 14:15. Preparations for the test were carried out, including the disabling of the emergency core cooling system. Meanwhile, another regional power station unexpectedly went offline. At 14:00, the Kiev electrical grid controller requested that the further reduction of Chernobyl's output be postponed, as power was needed to satisfy the peak evening demand, so the test was postponed.
Soon, the day shift was replaced by the evening shift. Despite the delay, the emergency core cooling system was left disabled. This system had to be disconnected via a manual isolating slide valve, which in practice meant that two or three people spent the whole shift manually turning sailboat-helm-sized valve wheels. The system would have no influence on the events that unfolded next, but allowing the reactor to run for 11 hours outside of the test without emergency protection was indicative of a general lack of safety culture.
At 23:04, the Kiev grid controller allowed the reactor shutdown to resume. This delay had some serious consequences: the day shift had long since departed, the evening shift was also preparing to leave, and the night shift would not take over until midnight, well into the job. According to plan, the test should have been finished during the day shift, and the night shift would only have had to maintain decay heat cooling systems in an otherwise shut-down plant.
The night shift had very limited time to prepare for and carry out the experiment. Anatoly Dyatlov, deputy chief-engineer of the Chernobyl Nuclear Power Plant (ChNPP), was present to supervise and direct the test. He was one of the test's chief authors and he was the highest-ranking individual present. Unit Shift Supervisor Aleksandr Akimov was in charge of the Unit 4 night shift, and Leonid Toptunov was the Senior Reactor Control Engineer responsible for the reactor's operational regimen, including the movement of the control rods. 25-year-old Toptunov had worked independently as a senior engineer for approximately three months.